MILCON Eastside Utilities Infrastructure, Bagram Air Base
The brief summary of the project:
The MILCON Eastside Utilities Infrastructure project is a comprehensive water treatment and distribution project which has a capacity of 15,000 cbm/day and consists of 12,000m of water distribution piping. Apart from these, project involves wells, utility bridges, utility connections, asphalt access roads and so forth.
Project Details
Project Type | Design – Build |
Project Location | Bagram, AFGHANISTAN |
Owner | USACE |
Project Start | 04 September 2012 |
Project End | 05 June 2014 |
The scope of the project:
The project was included four deep wells, two of them located in the vicinity of Water Treatment Plant #3 and installation of 12,000m of water distribution piping included all indicated valves, tees, bends, hydrants, service connections and other related appurtenances were carried out at the area. And also expansion of the Bagram Wastewater Treatment plant was included in the scope of the project.
Installation of 6,000m of gravity sanitary sewer collection pipes and 2,200 of sanitary force main pipes including manholes and service connections were executed at the Eastside area. In addition to the sewer piping, three sanitary sewer lift stations were installed and 3 utility bridges were constructed due to the elevation differences. WWTP expansion has concrete equalization and aeration tanks, Retaining Wall, WWTP Control Building, Headworks unit, and etc.
The Westside utility connections including the connection of thirteen (13) existing facilities to the base utility (water and sewer) network followed (Westside) Wells. The connections of facilities started from the WTP#1 through Facility #1 and completed from the other end with Facility #6A. Additional site work, demolition, electrical service and etc. have been performed during the construction works.